Tenon on First Front Wall Post – green oak barn
Thursday 10/12/20 Not much to report today. I got pulled off on to other jobs so only spent a couple of hours on the frame. But I did manage to get the tenon cut on the first post of the … Continue reading →
Marking Out – the green oak barn
The starting point for this project is a reinforced concrete raft foundation which is pretty level but not perfectly square. It is open on three sides with an existing wall bounding one of the short sides – the north side. … Continue reading →
The Cutting List – the green oak barn
With the frame plan in place, it was time to draw up the cutting list for the green oak. This was a nerve wracking experience. Get this wrong and the project would be severely delayed and costs would go up. … Continue reading →